AI data centers in Tennessee
Tennessee has 3 AI data centers on our list: 3 operational. They run about 1,333 MW today and plan 1.9 GW in total. The largest by live power is xAI Colossus 2 in Memphis (946 MW). Operators here: xAI and Meta. Data as of 9 Nov 2026.
Tennessee
3 sitesList of AI data centers in Tennessee
| Chips | Tenants | |||||||
|---|---|---|---|---|---|---|---|---|
| xAI Colossus 2 | 946est3 | 1,500est3 | Operational | xAI | Memphis, Tennessee | 2025-10 | NVIDIA GB200 / GB300 (Blackwell) | Part reportedxAI; Anthropic and Cursor reported as users (Epoch AI, citing company posts) |
| xAI Colossus 1 | 3001 | 3001 | Operational | xAI | Memphis, Tennessee | 2024 | NVIDIA H100, H200, GB200 | Anthropic |
| Meta Gallatin | 87est1 | 114est1 | Operational | Meta | Gallatin, Tennessee | 2026-08 | NVIDIA B300 (Epoch AI) | Meta |