EcoDataCenter 2 Borlänge (Mistral AI)
AI data center in Borlänge, Dalarna, Sweden, operated by EcoDataCenter.
EcoDataCenter's new campus in Borlänge, Sweden, where Mistral AI is the AI partner. The first two buildings were roofed in August 2026 with installation work due to finish by mid-2027.
- Live power
- —
- Planned power
- 67MW 4
- Status
- Under construction
- Accelerators
- —
Power: what each source says
Epoch AI estimates buildings 1-2 operational mid-2027 (24 MW IT) and buildings 3-4 mid-2028 (~48 MW IT / 67 MW facility), based on Bravida contract dates (estimates). EcoDataCenter has not published a total MW for the Mistral portion.
Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.
Tenants
Mistral AI
Campus facts
- Operator
- EcoDataCenter 1
- Owner / developer
- EcoDataCenter 1
- City
- Borlänge 1
- State / region
- Dalarna 1
- Country
- Sweden 1
- First power
- 2027 1
- Chips
- NVIDIA Rubin expected (Epoch AI) 1
- GPUs / accelerators
- Not published
- Cooling
- Not published
- Power source
- grid 1
- Coordinates
- 60.48° N, 15.44° E (town level)
- Verified
Sources
- EcoDataCenter: Mistral AI and EcoDataCenter partner in Sweden accessed 2026-11-09
- EcoDataCenter 2 campus overview accessed 2026-11-09
- Bravida: installations in two data centres in Borlänge (2026) accessed 2026-11-09
- Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09