EcoDataCenter 2 Borlänge (Mistral AI)

AI data center in Borlänge, Dalarna, Sweden, operated by EcoDataCenter.

EcoDataCenter's new campus in Borlänge, Sweden, where Mistral AI is the AI partner. The first two buildings were roofed in August 2026 with installation work due to finish by mid-2027.

Live power
— Nothing live yet
Planned power
67MW 4 Epoch AI estimate
Status
Under construction First power 2027
Accelerators
— No audited count published

Power: what each source says

Epoch AI estimates buildings 1-2 operational mid-2027 (24 MW IT) and buildings 3-4 mid-2028 (~48 MW IT / 67 MW facility), based on Bravida contract dates (estimates). EcoDataCenter has not published a total MW for the Mistral portion.

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

Mistral AI

Campus facts

Operator
EcoDataCenter 1
Owner / developer
EcoDataCenter 1
City
Borlänge 1
State / region
Dalarna 1
Country
Sweden 1
First power
2027 1
Chips
NVIDIA Rubin expected (Epoch AI) 1
GPUs / accelerators
Not published
Cooling
Not published
Power source
grid 1
Coordinates
60.48° N, 15.44° E (town level)
Verified

Sources

  1. EcoDataCenter: Mistral AI and EcoDataCenter partner in Sweden accessed 2026-11-09
  2. EcoDataCenter 2 campus overview accessed 2026-11-09
  3. Bravida: installations in two data centres in Borlänge (2026) accessed 2026-11-09
  4. Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09