Nscale Loughton
AI data center in Loughton, Essex, England, United Kingdom, operated by Nscale.
Nscale's planned 50 MW (up to 90 MW) AI site in Loughton, Essex, announced as a UK supercomputer for Microsoft. Grid power may not arrive until the 2030s and Microsoft reportedly withdrew in October 2026.
- Live power
- —
- Planned power
- 90MW 1
- Status
- Planned
- Accelerators
- —
Power: what each source says
50 MW initial, expandable to 90 MW (Nscale). The Guardian reported grid power may not be available until the early-to-mid 2030s; The Telegraph reported Microsoft's exit (2026-10-19).
Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.
Tenants
No tenant named in public sources.
Campus facts
Sources
- Baxtel: Microsoft exits Nscale's 50 MW Loughton deal (via The Telegraph, 2026-10) accessed 2026-11-09
- Data Centre Review: Nscale faces backlash over proposed data centre (2026-03) accessed 2026-11-09
- Capacity: Nscale to invest in UK data centres accessed 2026-11-09