AI data center in Horinger, Inner Mongolia, China, operated by Huawei.
Huawei Cloud's Inner Mongolia AI campus near Hohhot, running Ascend chips. Epoch AI estimates about 170 MW of IT power, roughly doubling by 2028.
Power: what each source says
Epoch AI estimates 170 MW IT / 212 MW facility as of 2026-08-18; projects ~351 MW IT / 439 MW facility by 2028-02 (estimate). Epoch withholds its sources for this site.
Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.
Tenants
No tenant named in public sources.
Campus facts
- Operator
- Huawei 1
- Owner / developer
- Huawei 1
- City
- Horinger 1
- State / region
- Inner Mongolia 1
- Country
- China 1
- First power
- 2025-06 1
- Chips
- Huawei Ascend 910C, Huawei Ascend 910B, Huawei Ascend 950DT (Epoch AI) 1
- GPUs / accelerators
- Not published
- Cooling
- Not published
- Power source
- Not published
- Coordinates
- 40.38° N, 111.82° E (town level)