Start Campus Sines (Nscale / Microsoft)
AI data center in Sines, Setúbal, Portugal, operated by Nscale.
Start Campus's 1.2 GW SINES campus on Portugal's Atlantic coast. In Q1 2026 Nscale deployed 12,600 Nvidia GB300 GPUs here for Microsoft, the EU's first GB300s.
Power: what each source says
1.2 GW full-campus plan (Start Campus factsheet). SIN01 in AI use from Q1 2026; Epoch AI estimates 33 MW IT as of 2026-08-16 and SIN02 (~200 MW more) operational ~2027-09 (estimate).
Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.
Tenants
Microsoft
Campus facts
Sources
- Start Campus hosts EU's first Nvidia GB300 chips with Nscale for Microsoft accessed 2026-11-09
- Start Campus: SINES accessed 2026-11-09
- Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09