Firmus Project Southgate (Melbourne)
AI data center in Melbourne, Victoria, Australia, operated by Firmus.
Firmus's Project Southgate AI factory in Melbourne, hosted at a CDC campus, with 18,400 Nvidia GB300 GPUs for a global hyperscale customer. Part of a wider Southgate build across Tasmania and mainland Australia.
- Live power
- 41MW 3
- Planned power
- —
- Status
- Operational
- Accelerators
- 18,400
Power: what each source says
No MW published by Firmus for Melbourne. Epoch AI estimates 41 MW IT operational ~2026-08-09 (estimate).
Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.
Tenants
Undisclosed global hyperscale customer
Campus facts
- Operator
- Firmus 1
- Owner / developer
- Firmus (CDC Data Centres as host, per Epoch AI) 1
- City
- Melbourne 1
- State / region
- Victoria 1
- Country
- Australia 1
- First power
- 2026 1
- Chips
- NVIDIA GB300 1
- GPUs / accelerators
- 18,400 1
- Cooling
- Not published
- Power source
- grid 1
- Coordinates
- 37.81° S, 144.96° E (town level)
- Verified
Sources
- Firmus: multi-year agreement with global hyperscale customer at Project Southgate accessed 2026-11-09
- Firmus expands Project Southgate across Australia accessed 2026-11-09
- Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09