Reliance-Meta Jamnagar AI data centre

AI data center in Jamnagar, Gujarat, India, operated by Reliance Industries.

A 168 MW AI data centre in Jamnagar, Gujarat that Reliance Industries will design, build and run, with capacity leased to Meta. Announced 10 June 2026 for delivery within two years.

Live power
— Nothing live yet
Planned power
168MW 1 Company
Status
Under construction First power 2028
Accelerators
— No audited count published

Power: what each source says

168 MW, delivery within two years of 2026-06-10, with an option to scale (Reliance). Meta separately backs ~1 GW of renewable power in India.

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

Meta

Campus facts

Operator
Reliance Industries 1
Owner / developer
Reliance Industries 1
City
Jamnagar 1
State / region
Gujarat 1
Country
India 1
First power
2028 1
Chips
Not published
GPUs / accelerators
Not published
Cooling
desalinated seawater cooling (stated) 1
Power source
renewable (stated) 1
Coordinates
22.47° N, 70.06° E (town level)
Verified

Sources

  1. Reliance media release: Reliance and Meta to develop AI-enabled data centre in Jamnagar (2026-06-10) accessed 2026-11-09
  2. ThePrint: Meta, Reliance team up to build 168 MW AI data centre accessed 2026-11-09