Pure DC Seinäjoki SJK01

AI data center in Seinäjoki, Finland.

Pure DC is building a dedicated AI campus in Finland. The stated buildout is 110 MW.

Live power
— Nothing live yet
Planned power
110MW 1 Company
Status
Under construction First power not announced
Accelerators
— No audited count published

Power: what each source says

Phase 1 will deliver 110 MW of IT capacity; further expansion is potential.

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

No tenant named in public sources.

Campus facts

Tier
Dedicated AI campus 1
Operator
Not published
Owner / developer
Pure DC 1
City
Seinäjoki 1
State / region
Not published
Country
Finland 1
First power
Not published
Chips
Not published
GPUs / accelerators
Not published
Cooling
air and direct liquid cooling 1
Power source
Not published
Coordinates
62.79° N, 22.83° E (town level)
Verified

Sources

  1. Source accessed 2026-11-18