Lambda Kansas City AI factory

AI data center in Kansas City, Missouri, operated by Lambda.

Lambda's conversion of a vacant 2009 building in Kansas City, Missouri into an AI factory for one customer under a multi-year deal. 24 MW to start with 10,000+ Nvidia Blackwell Ultra GPUs, scaling past 100 MW.

Live power
— Nothing live yet
Planned power
100MW 1 Company
Status
Planned First power 2026
Accelerators
10,000 Stated by the company

Power: what each source says

24 MW initial, 100+ MW potential (Lambda, 2025-10). Launch targeted early 2026; no public go-live confirmation found as of 2026-11-09.

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

Single undisclosed Lambda customer

Campus facts

Operator
Lambda 1
Owner / developer
Lambda 1
City
Kansas City 1
State / region
Missouri 1
Country
United States 1
First power
2026 1
Chips
NVIDIA Blackwell Ultra (more than 10,000) 1
GPUs / accelerators
10,000 1
Cooling
Not published
Power source
grid 1
Coordinates
39.10° N, 94.58° W (town level)
Verified

Sources

  1. Lambda: building a 100 MW AI factory in Kansas City, MO accessed 2026-11-09
  2. KCTV5: $500 million supercomputer facility for Kansas City (2025-10-28) accessed 2026-11-09