Stargate New Mexico (Project Jupiter)
AI data center in Santa Teresa area, New Mexico, operated by Oracle (for OpenAI).
Project Jupiter in Doña Ana County, New Mexico, a Stargate site for OpenAI with Oracle as operator. Power comes from on-site gas microgrids, with Bloom Energy fuel cells announced in April 2026.
- Live power
- —
- Planned power
- 2,200MW 3
- Status
- Under construction
- Accelerators
- —
Power: what each source says
Epoch AI's April 2026 review projects ~2.2 GW by Q4 2028 (Epoch timeline: 1,750 MW IT / 2,450 MW facility). No company-stated MW total found. Epoch satellite review, 2026-06-22: structural work underway, nothing operational.
Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.
Tenants
OpenAI
Campus facts
- Operator
- Oracle (for OpenAI) 1
- Owner / developer
- BorderPlex Digital Assets (Project Jupiter developer, per Oracle release) 1
- City
- Santa Teresa area 1
- State / region
- New Mexico (Doña Ana County) 1
- Country
- United States 1
- First power
- Not published
- Chips
- Not published
- GPUs / accelerators
- Not published
- Cooling
- Not published
- Power source
- gas microgrids and Bloom Energy fuel cells (on-site) 1
- Coordinates
- 31.86° N, 106.67° W (town level)
- Verified
Sources
- Project Jupiter website accessed 2026-11-09
- Oracle, BorderPlex and Bloom Energy to power Project Jupiter with fuel cells (2026-04-27) accessed 2026-11-09
- Epoch AI: OpenAI Stargate, where the US sites stand (licence: CC BY 4.0) accessed 2026-11-09