Galaxy Helios (CoreWeave)

AI data center in Afton, Texas, operated by CoreWeave.

Galaxy Digital's Helios campus in Dickens County, West Texas, fully leased to CoreWeave in three phases. Phase I was due by mid-2026, Phase II through 2027 and Phase III from 2028.

Live power
132MW 3 Epoch AI estimate, as of 2026-08-30
Planned power
800MW 1 Company
Status
Operational First power 2026
Accelerators
— No audited count published

Power: what each source says

Galaxy Q3 2025: ~800 MW of critical IT committed to CoreWeave across three phases. Epoch AI estimates building 1 (132 MW IT / 200 MW facility) operational ~2026-08-30 and ~528 MW IT / 800 MW facility by 2029 (estimates).

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

CoreWeave

Campus facts

Operator
CoreWeave 1
Owner / developer
Galaxy Digital 1
City
Afton 1
State / region
Texas (Dickens County) 1
Country
United States 1
First power
2026 1
Chips
NVIDIA Blackwell (Epoch AI) 1
GPUs / accelerators
Not published
Cooling
Not published
Power source
grid (ERCOT) 1
Coordinates
33.77° N, 100.82° W (town level)
Verified

Sources

  1. Galaxy Q3 2025 financial results accessed 2026-11-09
  2. Galaxy: data centers accessed 2026-11-09
  3. Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09