QTS Richmond 3

AI data center in Sandston, Virginia, operated by QTS Data Centers.

QTS's newest Sandston, Virginia campus. Buildings 2 and 3 are live at about 144 MW of IT power, heading to roughly 240 MW (Epoch AI).

Live power
144MW 1 Epoch AI estimate, as of 2026-05-14
Planned power
336MW 1 Epoch AI estimate
Status
Operational First power 2026-02
Accelerators
— No audited count published

Power: what each source says

Epoch AI estimates 144 MW IT / 202 MW facility as of 2026-05-14; projects ~240 MW IT / 336 MW facility by 2027-02 (estimate).

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

No tenant named in public sources.

Campus facts

Operator
QTS Data Centers 1
Owner / developer
QTS Data Centers (Blackstone) 1
City
Sandston 1
State / region
Virginia (Henrico County) 1
Country
United States 1
First power
2026-02 1
Chips
Not published
GPUs / accelerators
Not published
Cooling
Not published
Power source
grid (Dominion Energy) 1
Coordinates
37.52° N, 77.32° W (town level)
Verified

Sources

  1. Epoch AI data center profile: QTS Richmond 3 (CC-BY 4.0) (licence: CC BY 4.0) accessed 2026-11-09
  2. Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09