Meta's Temple, Texas campus, built by JE Dunn. Building 3 came online in September 2026, taking the site to about 178 MW of IT power (Epoch AI).

Live power
178MW 1 Epoch AI estimate, as of 2026-09-30
Planned power
231MW 1 Epoch AI estimate
Status
Operational First power 2025-12
Accelerators
— No audited count published

Power: what each source says

Epoch AI estimates 178 MW IT / 231 MW facility as of 2026-09-30. JE Dunn lists a 152 MW power capacity for the original buildings.

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

Meta

Campus facts

Operator
Meta 1
Owner / developer
Meta 1
City
Temple 1
State / region
Texas 1
Country
United States 1
First power
2025-12 1
Chips
NVIDIA B300 (Epoch AI) 1
GPUs / accelerators
Not published
Cooling
Not published
Power source
Not published
Coordinates
31.10° N, 97.34° W (town level)
Verified

Sources

  1. Epoch AI data center profile: Meta Temple (CC-BY 4.0) (licence: CC BY 4.0) accessed 2026-11-09
  2. Meta: site page or announcement accessed 2026-11-09
  3. Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09