Google Kansas City (Hunt Midwest)

AI data center in Kansas City, Missouri, operated by Google.

Google's $1B data center at the Hunt Midwest Business Center in Kansas City, Missouri. Building 1 came online around August 2026 at about 105 MW of IT power by Epoch AI's estimate.

Live power
105MW 1 Epoch AI estimate, as of 2026-08-01
Planned power
126MW 1 Epoch AI estimate
Status
Operational First power 2026-08
Accelerators
— No audited count published

Power: what each source says

Epoch AI estimates 105 MW IT / 126 MW facility as of 2026-08-01.

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

Google

Campus facts

Operator
Google 1
Owner / developer
Google 1
City
Kansas City 1
State / region
Missouri 1
Country
United States 1
First power
2026-08 1
Chips
Not published
GPUs / accelerators
Not published
Cooling
Not published
Power source
Not published
Coordinates
39.10° N, 94.58° W (town level)
Verified

Sources

  1. Epoch AI data center profile: Google Kansas City East (CC-BY 4.0) (licence: CC BY 4.0) accessed 2026-11-09
  2. Google: site page or announcement accessed 2026-11-09