Meta Eagle Mountain

AI data center in Eagle Mountain, Utah, operated by Meta.

Meta's expanded Eagle Mountain, Utah campus, built by Mortenson. Buildings 1 and 2 of the AI expansion are live at about 133 MW of IT power (Epoch AI).

Live power
133MW 1 Epoch AI estimate, as of 2026-05-02
Planned power
179MW 1 Epoch AI estimate
Status
Operational First power 2025-12
Accelerators
— No audited count published

Power: what each source says

Epoch AI estimates 133 MW IT / 179 MW facility as of 2026-05-02. Williams is building a gas-fired plant next to the campus (air permit application, Feb 2026).

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

Meta

Campus facts

Operator
Meta 1
Owner / developer
Meta 1
City
Eagle Mountain 1
State / region
Utah 1
Country
United States 1
First power
2025-12 1
Chips
NVIDIA B300 (Epoch AI) 1
GPUs / accelerators
Not published
Cooling
Not published
Power source
grid plus adjacent Williams gas plant (under construction) 1
Coordinates
40.31° N, 112.01° W (town level)
Verified

Sources

  1. Epoch AI data center profile: Meta Eagle Mountain (CC-BY 4.0) (licence: CC BY 4.0) accessed 2026-11-09
  2. Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09