CoreWeave Lancaster

AI data center in Lancaster, Pennsylvania, operated by CoreWeave.

CoreWeave's $6 billion plan to build AI data centers on two former printing-press sites in Lancaster, Pennsylvania. The first building was still being fitted out in July 2026.

Live power
— Nothing live yet
Planned power
300MW 1 Company
Status
Under construction First power 2027
Accelerators
— No audited count published

Power: what each source says

CoreWeave (2025-07-15): 100 MW initial, potential to 300 MW, $6B. Epoch AI estimates building 1 (~92 MW IT) operational ~mid-2027 (estimate).

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

No tenant named in public sources.

Campus facts

Operator
CoreWeave 1
Owner / developer
CoreWeave (Blue Owl as investor per Epoch AI) 1
City
Lancaster 1
State / region
Pennsylvania 1
Country
United States 1
First power
2027 1
Chips
Not published
GPUs / accelerators
Not published
Cooling
Not published
Power source
grid (PJM) 1
Coordinates
40.04° N, 76.31° W (town level)
Verified

Sources

  1. CoreWeave: multi-billion-dollar commitment to AI infrastructure in Pennsylvania (2025-07-15) accessed 2026-11-09
  2. WITF: Lancaster city data centers face zoning hearing accessed 2026-11-09
  3. Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09