Google Cedar Rapids

AI data center in Cedar Rapids, Iowa, operated by Google.

Google's Cedar Rapids, Iowa campus, with a 600 MW load request filed with MISO. Building 1 is due around end-2026 and Epoch AI projects about 261 MW of IT power by mid-2027.

Live power
— Nothing live yet
Planned power
314MW 1 Epoch AI estimate
Status
Under construction First power 2026-12
Accelerators
— No audited count published

Power: what each source says

Nothing live per Epoch AI satellite review of 2026-04-16; projects ~261 MW IT / 314 MW facility by 2027-05 (estimate). Epoch projects first building operational ~2026-12 (estimate). MISO new-load announcement lists 600 MW for Google in Cedar Rapids.

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

Google

Campus facts

Operator
Google 1
Owner / developer
Google 1
City
Cedar Rapids 1
State / region
Iowa 1
Country
United States 1
First power
2026-12 1
Chips
Not published
GPUs / accelerators
Not published
Cooling
Not published
Power source
Not published
Coordinates
41.98° N, 91.67° W (town level)
Verified

Sources

  1. Epoch AI data center profile: Google Cedar Rapids (CC-BY 4.0) (licence: CC BY 4.0) accessed 2026-11-09
  2. Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09