AI data center in McCarran (Tahoe Reno Industrial Center), Nevada, operated by Google.

Google's Nevada campus at the Tahoe Reno Industrial Center. Epoch AI estimates about 161 MW of IT power today and about 300 MW once buildings 3-4 are done in 2027.

Live power
161MW 1 Epoch AI estimate, as of 2026-04-13
Planned power
389MW 1 Epoch AI estimate
Status
Operational First power 2023
Accelerators
— No audited count published

Power: what each source says

Epoch AI estimates 161 MW IT / 214 MW facility as of 2026-04-13; projects ~300 MW IT / 389 MW facility by 2027-06 (estimate).

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

Google

Campus facts

Operator
Google 1
Owner / developer
Google 1
City
McCarran (Tahoe Reno Industrial Center) 1
State / region
Nevada (Storey County) 1
Country
United States 1
First power
2023 1
Chips
Google TPU v5e, Google TPU v4, Google TPU v6e, Google TPU v5p (Epoch AI) 1
GPUs / accelerators
Not published
Cooling
Not published
Power source
Not published
Coordinates
39.53° N, 119.47° W (town level)
Verified

Sources

  1. Epoch AI data center profile: Google Storey County (CC-BY 4.0) (licence: CC BY 4.0) accessed 2026-11-09
  2. Google: site page or announcement accessed 2026-11-09