xAI Atlanta (QTS)

AI data center in Atlanta, Georgia, operated by xAI (SpaceXAI, part of SpaceX since 2026).

xAI's smaller Atlanta cluster in a QTS building, shared with X and backed by about $700M of AI equipment per county bond documents. Epoch AI estimates about 17 MW of IT power.

Live power
17MW 1 Epoch AI estimate, as of 2026-07-10
Planned power
24MW 1 Epoch AI estimate
Status
Operational First power 2025-02
Accelerators
— No audited count published

Power: what each source says

Epoch AI estimates 17 MW IT / 24 MW facility as of 2026-07-10. Develop Fulton bond fact sheet (Jan 2024) and Fortune (Jan 2025) describe the X/xAI equipment.

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

xAI; X Corp

Campus facts

Operator
xAI (SpaceXAI, part of SpaceX since 2026) 1
Owner / developer
QTS Data Centers (building) 1
City
Atlanta 1
State / region
Georgia 1
Country
United States 1
First power
2025-02 1
Chips
NVIDIA H100, NVIDIA A100 (Epoch AI) 1
GPUs / accelerators
Not published
Cooling
Not published
Power source
Not published
Coordinates
33.75° N, 84.39° W (town level)
Verified

Sources

  1. Epoch AI data center profile: xAI QTS Atlanta (CC-BY 4.0) (licence: CC BY 4.0) accessed 2026-11-09
  2. Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09