Meta El Paso

AI data center in El Paso, Texas, operated by Meta.

Meta's El Paso, Texas campus, broken ground in October 2025 and raised in March 2026 from $1.5B to $10B for about 1 GW. Interim power comes from Enchanted Rock gas units.

Live power
— Nothing live yet
Planned power
1,000MW 1 Company
Status
Under construction First power not announced
Accelerators
— No audited count published

Power: what each source says

About 1 GW by 2028 (Meta, March 2026); one report says 2029. Interim supply: 366 MW of Enchanted Rock gas units plus 220 MW from El Paso Electric.

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

Meta

Campus facts

Operator
Meta 1
Owner / developer
Meta 1
City
El Paso 1
State / region
Texas 1
Country
United States 1
First power
Not published
Chips
Not published
GPUs / accelerators
Not published
Cooling
Not published
Power source
gas (on-site modular) plus grid (El Paso Electric) 1
Coordinates
31.76° N, 106.49° W (town level)
Verified

Sources

  1. DCD: Meta files to expand El Paso campus with 12 new buildings accessed 2026-11-09
  2. AI Business: Meta ups Texas AI data center investment from $1.5B to $10B accessed 2026-11-09
  3. Baxtel: Meta plans 366 MW of modular gas units for El Paso accessed 2026-11-09