Applied Digital Polaris Forge 1 (Ellendale)

AI data center in Ellendale, North Dakota, operated by CoreWeave.

Applied Digital's purpose-built AI campus in Ellendale, North Dakota, leased to CoreWeave for 400 MW across three buildings.

Live power
68MW 4 Epoch AI estimate, as of 2026-06-30
Planned power
400MW 1 Company
Status
Operational First power 2025-10
Accelerators
— No audited count published

Power: what each source says

400 MW leased to CoreWeave across three buildings (Applied Digital). Building 1 live 2025; second building delivered (Applied Digital release); building 3 due H1 2027. Epoch AI estimates 68 MW IT as of 2026-06-30.

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

CoreWeave

Campus facts

Operator
CoreWeave 1
Owner / developer
Applied Digital 1
City
Ellendale 1
State / region
North Dakota 1
Country
United States 1
First power
2025-10 1
Chips
NVIDIA Blackwell (Epoch AI) 1
GPUs / accelerators
Not published
Cooling
Not published
Power source
grid 1
Coordinates
46.00° N, 98.53° W (town level)
Verified

Sources

  1. Applied Digital delivers second building at Polaris Forge 1 accessed 2026-11-09
  2. Applied Digital announces 250 MW lease with CoreWeave accessed 2026-11-09
  3. Applied Digital finalizes additional 150 MW lease accessed 2026-11-09
  4. Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09