Meta Bowling Green (Middleton Township)
AI data center in Bowling Green, Ohio, operated by Meta.
A Meta AI campus near Bowling Green, Ohio, paired with the 350 MW behind-the-meter Apollo gas plant. Buildings 1-2 were under construction in mid-2026.
- Live power
- —
- Planned power
- 570MW 2
- Status
- Under construction
- Accelerators
- —
Power: what each source says
Epoch AI projects ~422 MW IT / 570 MW facility once four buildings are done (~2028) and building 1 operational ~2027-02 (estimates). Apollo Power Generation Project: 350 MW (Ohio Power Siting Board).
Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.
Tenants
Meta
Campus facts
- Operator
- Meta 1
- Owner / developer
- Meta 1
- City
- Bowling Green 1
- State / region
- Ohio 1
- Country
- United States 1
- First power
- 2027 1
- Chips
- Not published
- GPUs / accelerators
- Not published
- Cooling
- Not published
- Power source
- gas (on-site Apollo plant, Williams) plus grid 1
- Coordinates
- 41.37° N, 83.65° W (town level)
- Verified
Sources
- Ohio Power Siting Board announcement (archived) accessed 2026-11-09
- Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09