Meta Prometheus (New Albany)
AI data center in New Albany, Ohio, operated by Meta.
Meta's first gigawatt-scale AI training cluster in New Albany, Ohio, mixing permanent buildings, tent structures and leased Vantage halls. On-site gas plants (Socrates projects) add power.
Power: what each source says
About 1 GW announced by Meta for 2026. Epoch AI estimates 471 MW IT / 612 MW facility as of 2026-08-31 and ~1 GW IT by mid-2028 (estimate).
Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.
Tenants
Meta
Campus facts
- Operator
- Meta 1
- Owner / developer
- Meta (plus leased halls from Vantage Data Centers) 1
- City
- New Albany 1
- State / region
- Ohio 1
- Country
- United States 1
- First power
- 2025-10 1
- Chips
- NVIDIA GB300 (Epoch AI) 1
- GPUs / accelerators
- Not published
- Cooling
- liquid 1
- Power source
- grid (AEP Ohio) plus on-site gas (Williams 'Socrates' projects) 1
- Coordinates
- 40.08° N, 82.81° W (town level)
- Verified
Sources
- Meta Engineering: Meta's infrastructure evolution and the advent of AI (2025-09-29) accessed 2026-11-09
- ITPro: Meta's Prometheus and Hyperion superclusters accessed 2026-11-09
- Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09