Meta Prometheus (New Albany)

AI data center in New Albany, Ohio, operated by Meta.

Meta's first gigawatt-scale AI training cluster in New Albany, Ohio, mixing permanent buildings, tent structures and leased Vantage halls. On-site gas plants (Socrates projects) add power.

Live power
471MW 3 Epoch AI estimate, as of 2026-08-31
Planned power
1,000MW 1 Company
Status
Operational First power 2025-10
Accelerators
— No audited count published

Power: what each source says

About 1 GW announced by Meta for 2026. Epoch AI estimates 471 MW IT / 612 MW facility as of 2026-08-31 and ~1 GW IT by mid-2028 (estimate).

Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.

Tenants

Meta

Campus facts

Operator
Meta 1
Owner / developer
Meta (plus leased halls from Vantage Data Centers) 1
City
New Albany 1
State / region
Ohio 1
Country
United States 1
First power
2025-10 1
Chips
NVIDIA GB300 (Epoch AI) 1
GPUs / accelerators
Not published
Cooling
liquid 1
Power source
grid (AEP Ohio) plus on-site gas (Williams 'Socrates' projects) 1
Coordinates
40.08° N, 82.81° W (town level)
Verified

Sources

  1. Meta Engineering: Meta's infrastructure evolution and the advent of AI (2025-09-29) accessed 2026-11-09
  2. ITPro: Meta's Prometheus and Hyperion superclusters accessed 2026-11-09
  3. Epoch AI, AI data centers dataset (CC-BY 4.0, updated 2026-11-06) (licence: CC BY 4.0) accessed 2026-11-09