Fermi America Project Matador (HyperGrid)
AI data center in Amarillo area, Texas, operated by Fermi America.
Fermi America's private-grid AI campus beside Pantex near Amarillo, Texas, now projected at 17 GW. TensorWave signed a 15-year lease for the first 222 MW of AMD GPU capacity in August 2026, and the first gas turbines are on site.
- Live power
- —
- Planned power
- 17,000MW 1
- Status
- Under construction
- Accelerators
- —
Power: what each source says
Fermi (2026-08-10): campus expected to ramp to ~17 GW of private power, ~6 GW of it permitted. First lease: TensorWave, 222 MW total facility power in phase 1 with rights to 650+ MW over three phases, ~$6.5B over 15 years; phased delivery from H2 2027. AMD signed credit support for the first 222 MW IT deployment. First gas turbines delivered; gas, water and transmission lines installed (Fermi shareholder meeting, 2026-11-02). NRC staff supports a combined licence for four AP1000 reactors (2026).
Figures labelled Epoch AI are estimates from satellite imagery, permits and filings. Company figures come from the operator, owner or its filings. IT power is what the servers draw; in Epoch AI’s figures for these campuses it runs about 15–35% below total facility power.
Tenants
TensorWave (binding lease, phase 1: 222 MW)
Campus facts
- Operator
- Fermi America 1
- Owner / developer
- Fermi America 1
- City
- Amarillo area 1
- State / region
- Texas (Carson County) 1
- Country
- United States 1
- First power
- 2027 1
- Chips
- AMD Instinct (TensorWave lease) 1
- GPUs / accelerators
- Not published
- Cooling
- Not published
- Power source
- on-site gas turbines (Siemens Energy); nuclear (4x AP1000) licensed for later phases 1
- Coordinates
- 35.32° N, 101.56° W (town level)
- Verified
Sources
- Fermi: binding lease agreement with TensorWave (2026-08-10) accessed 2026-11-09
- MarketBeat: Fermi advances Project Matador, pivots to powered-land strategy (2026-11-02) accessed 2026-11-09
- NucNet: US regulator supports licence for four AP1000 reactors at Project Matador accessed 2026-11-09
- Fox34: Project Matador construction paused awaiting clean air permit (2026-02-06) accessed 2026-11-09
- ABC7 Amarillo: Fermi America statement after losing first tenant funding accessed 2026-11-09
- Converge Digest: Fermi America resets timeline for Project Matador accessed 2026-11-09